Work for the Week of 9/1/2014

  • New traffic signal turn on Tuesday 9/2.
  • Remove Work Zone Speed Limit restrictions.
  • Coring of pavement for final thickness determination.
  • Touch up damaged pavement markings.
  • Install raised reflective pavement markers.

Work for the Week of 8/25/2014

  • Touch up damaged pavement markings.
  • Install raised reflective pavement markers.
  • Miscellaneous clean up work and site punch list work.
  • New traffic signal turn on is currently scheduled for Tuesday 9/2 (weather permitting).

Work for the Week of 8/18/2014

  • Form-liner staining on the MSE walls and parapets.
  • Miscellaneous clean up work and site punch list work.
  • Final diamond grinding of PCC pavement surface scheduled for Saturday 8/23.
  • New traffic signal turn on is scheduled for 9/2/14 (weather permitting).

Work for the Week of 8/4/2014

  • Painting of textured surfaces on the MSE walls.
  • Miscellaneous clean up and punch list work.
  • Installation of cable for new traffic signal.
  • Installation of poles and mast arms for the new traffic signal.
  • Install lane line reflectors on Fairfield and IL 176.

 

Work for the Week of 7/28/2014

  • Pour curb and gutter around island at the SE quadrant.
  • Finish micro grinding of pavement to correct surface variations on the NB and SB lanes of Fairfield.
  • Pour concrete median surface in the island at the SE quadrant.
  • Micro grinding of pavement to correct surface variations on EB lanes of IL 176.
  • Install guardrail on the north side of IL 176.
  • Install final pavement markings and reflectors on Fairfield and IL 176
  • Weather permitting the Contractor will be opening all lanes of traffic at the end of the week.

Work for the Week of 7/21/2014

  • Pour curb and gutter around island at the SE quadrant.
  • Auger and pour mast arm foundations for traffic signal at NE and SE quadrants.
  • Micro grinding of pavement to correct surface variations on WB lanes of IL 176.
  • Re-align traffic on NB and SB Fairfield.
  • Micro grinding of pavement to correct surface variations on the NB and SB lanes of Fairfield.
  • Finish up parkway restoration at the NE and SW quadrants.
  • Re-align traffic on EB and WB IL 176 at the end of the week.
  • Remove and replace cracked pavement panels on eastbound IL 176.

Work for the Week of 7/14/2014

  • Pour concrete pavement panels in northeast corner of the intersection of Fairfield and IL 176.
  • Aggregate shoulder on the east and west sides of Fairfield north of Hafer.
  • Parkway restoration along the north side of IL 176 east leg.
  • Parkway restoration along the east side of Fairfield North leg.
  • Mill and resurface asphalt pavement on IL 176 at the east and west limits.
  • Mill and resurface asphalt pavement on Fairfield at the south limit.
  • Install fiber optic cable for the traffic signal interconnect between IL 176 and Bonner.

Work for the Week of 7/7/2014

  • Pour concrete pavement panels at the south end of Fairfield by Ivanhoe.
  • Pour concrete pavement panels in the intersection of Fairfield and IL 176.
  • Final pavement markings on Fairfield north of Cardinal Court.
  • Pour concrete curb and gutter on west leg of IL 176 on the north side.
  • Install underground conduit and foundations for the new traffic signal at Fairfield and IL 176.
  • Aggregate shoulder on the east side of Fairfield north of Hafer.
  • Shift northbound traffic on Fairfield to the west at the end of the week (weather pending).