Work for the Week of 9/1/2014

  • New traffic signal turn on Tuesday 9/2.
  • Remove Work Zone Speed Limit restrictions.
  • Coring of pavement for final thickness determination.
  • Touch up damaged pavement markings.
  • Install raised reflective pavement markers.

Work for the Week of 8/25/2014

  • Touch up damaged pavement markings.
  • Install raised reflective pavement markers.
  • Miscellaneous clean up work and site punch list work.
  • New traffic signal turn on is currently scheduled for Tuesday 9/2 (weather permitting).

Work for the Week of 8/18/2014

  • Form-liner staining on the MSE walls and parapets.
  • Miscellaneous clean up work and site punch list work.
  • Final diamond grinding of PCC pavement surface scheduled for Saturday 8/23.
  • New traffic signal turn on is scheduled for 9/2/14 (weather permitting).

Work for the Week of 8/4/2014

  • Painting of textured surfaces on the MSE walls.
  • Miscellaneous clean up and punch list work.
  • Installation of cable for new traffic signal.
  • Installation of poles and mast arms for the new traffic signal.
  • Install lane line reflectors on Fairfield and IL 176.

 

Work for the Week of 7/28/2014

  • Pour curb and gutter around island at the SE quadrant.
  • Finish micro grinding of pavement to correct surface variations on the NB and SB lanes of Fairfield.
  • Pour concrete median surface in the island at the SE quadrant.
  • Micro grinding of pavement to correct surface variations on EB lanes of IL 176.
  • Install guardrail on the north side of IL 176.
  • Install final pavement markings and reflectors on Fairfield and IL 176
  • Weather permitting the Contractor will be opening all lanes of traffic at the end of the week.

Work for the Week of 7/21/2014

  • Pour curb and gutter around island at the SE quadrant.
  • Auger and pour mast arm foundations for traffic signal at NE and SE quadrants.
  • Micro grinding of pavement to correct surface variations on WB lanes of IL 176.
  • Re-align traffic on NB and SB Fairfield.
  • Micro grinding of pavement to correct surface variations on the NB and SB lanes of Fairfield.
  • Finish up parkway restoration at the NE and SW quadrants.
  • Re-align traffic on EB and WB IL 176 at the end of the week.
  • Remove and replace cracked pavement panels on eastbound IL 176.

Work for the Week of 7/14/2014

  • Pour concrete pavement panels in northeast corner of the intersection of Fairfield and IL 176.
  • Aggregate shoulder on the east and west sides of Fairfield north of Hafer.
  • Parkway restoration along the north side of IL 176 east leg.
  • Parkway restoration along the east side of Fairfield North leg.
  • Mill and resurface asphalt pavement on IL 176 at the east and west limits.
  • Mill and resurface asphalt pavement on Fairfield at the south limit.
  • Install fiber optic cable for the traffic signal interconnect between IL 176 and Bonner.

Work for the Week of 7/7/2014

  • Pour concrete pavement panels at the south end of Fairfield by Ivanhoe.
  • Pour concrete pavement panels in the intersection of Fairfield and IL 176.
  • Final pavement markings on Fairfield north of Cardinal Court.
  • Pour concrete curb and gutter on west leg of IL 176 on the north side.
  • Install underground conduit and foundations for the new traffic signal at Fairfield and IL 176.
  • Aggregate shoulder on the east side of Fairfield north of Hafer.
  • Shift northbound traffic on Fairfield to the west at the end of the week (weather pending).

Traffic Alert: New Southbound Lanes Open on Fairfield

The new southbound lanes of Fairfield have been opened through the entire length of the project.

The Contractors will now begin work on building the new concrete pavement in the mddle portion of the intersection.  This traffic configuration is expected to be in place for about two weeks.

Please BE ALERT and pay attention ot the traffic control signage when driving through the project.

We are getting close to the end of the project.  Your patience and cooperation are appreciated.